Work wrapping up at the Quarry, starting on De Zavala

Crews opened all the new lanes on Jones-Maltsberger at the railroad tracks by the Quarry this past weekend.  Finish-up work should be completed by Thanksgiving, just in time for the Christmas shopping frenzy.  As you may recall, work began there earlier this year to finally remove the long-standing bottleneck between the Quarry and US 281.  Work was expected to be finished last month, but this year’s unusual rain delayed things just a bit.

Meanwhile, work began last month on a long-awaited (or maybe long-feared) project to widen De Zavala between Babcock and Cogburn.  The project will widen the road to five lanes (two each way plus a center left-turn lane) and add sidewalks, curbs, and updated traffic signals.  The $17 million project is expected to be completed in mid 2012.

 